Join Mike from St. Thomas Economic Development and Pat Anckaert from the City of St. Thomas Industrial Development Team on-site to learn more about the Highbury Ave Widening Project's current status.
Highlights from today's update: Sanitary Trunk Main: Connecting to the Harper Road pump station to manage flows from Yarmouth Yards to the pollution control plant on Sunset. Water Main Installation: A 750mm diameter main, one of the largest in the city, feeding Central Elgin and Southwold. Highbury Progress: Widening to the east with curb installation coming soon. - Granular A, asphalt, and line markings to follow. - Traffic flip to the east side of Highbury is anticipated by the end of July. - Ongoing works at Ron McNeil and Highbury roundabout, Centennial, and Highway 3. 🛣️ Looking ahead: December 2024: Expected completion of the base coat asphalt on Highbury. Spring 2025: Final surface coat, line markings, hydroseeding, and signage.