Mike from St. Thomas Economic Development is back—this time reporting from a parking lot that's paving the way (literally) for the future PowerCo facility in St. Thomas.
In this update, Mike chats with Nathan Bokma about how this space will be used as the construction work progresses: ✔️ Truck traffic access off Electric Avenue ✔️ Employee parking for over 1,200 vehicles ✔️ On-site storage for sea cans and specialized equipment ✔️ Staging ground for temporary offices and materials during construction They also dive into the details of drainage design (spoiler: it’s all about the slope), talk about J-AAR Excavating’s great paving work, and give a quick update on nearby Hydro One and Highbury Avenue projects. And yes, we answer the age-old question: is it asphalt or ash-fault?